Restoration work is nearly complete!

It’s been a while since the last project update, so here we go. As many of you have been following the time capsule story, the restoration project that led to its discovery has been moving towards completion.

By the end of October the masonry restoration on the west façade was finished, deteriorated wood at the windows and door surround was replaced, and painting was completed. At the start of November the scaffolding came down to reveal a newly pointed and painted façade, although the average person walking by would likely not notice the work done. That is our goal during restoration projects, to make the necessary repairs and replacements without it appearing that we did anything.

The work on the east façade continued as well. The balcony balustrade and moldings were repaired and reinstalled. A late October storm caused damage to the window below the clock, so repairing that window was added to the project, and it has since returned with a new frame that exactly matches the previous one. Replacement of the balcony doors is being worked on as we speak, with new doors being fabricated due to the deterioration found on the old ones after removal and striping of the paint. Painting of the wood work on the east façade is in progress.

Most recently, the Lion and Unicorn statues were returned to the building after slightly more than two months away for restoration. Skylight Studios repaired and regilded the statues, the Lion in gold and the Unicorn in palladium. The new time capsule fabricated and donated by John F. Shea Co. could be seen from below as the crane from Marr Rigging lifted the Lion up to be secured in place by the crew from NER Building Restoration. All the while our general contractor Commodore Builders ensured a smooth day.

As the project comes to substantial completion, the Society needs a few more days of good weather and continued good work from all involved in the project.

By Matt Ottinger, Director of Facilities and Historic Preservation